The finish is looking good! Just the back of the house to do now, although I imagine they'll be rained off for the rest of the week if the forecast is to be believed.
A blog to record the progress of our house ' do-er-upper' project. It will act as a memory book to record everything we went through on our house renovation project, the before and after and our trials and tribulations. Here's hoping for a nice and easy, straight forward, house renovation project!
Wednesday, 28 October 2015
Tuesday, 27 October 2015
Wednesday, 21 October 2015
Sunday, 18 October 2015
Full house
Just a few more tiles to go on , followed by the ridge tiles as that should be us watertight! Well... from the roof anyway. We still need windows and doors.
Wednesday, 14 October 2015
Tuesday, 13 October 2015
Tuesday, 6 October 2015
Not so flat roof
There was a small window of opportunity today before the rain arrived, so more tiles went on the back roof. They're big tiles because of the shallow pitch but that means they go on quickly!
Saturday, 3 October 2015
Water-tight?
The whole roof is now felted, so we should be more or less watertight now! I really hope we are as we're expecting rain this weekend...
Thursday, 1 October 2015
Tiles
The valleys are done and there is only a bit of the roof that still needs covering with membrane. Tiles have also started going on now - it's looking great!